1st Quarterly Report Submitted to ICMA

The first project report has been submitted to ICMA. We reported these major accomplishments/activities.

Net metering application has been filed with American Electric Power (AEP).
Currently refining scope of work needed for City permits and team clarity.
Professors have begun the student selection process for this project.
Solar panel analysis is underway. Current market and demand could drive costs [...]

Project Timeline

Timeline: Solar Test Bed Project at the Fayetteville Public Library

 

The project will begin in the fall of 2009. Students in the senior design class at the University of Arkansas’ College of Engineering will design, construct and install with the latest “off the shelf” technology for a grid-tied solar application, including an inverter and 48 solar [...]